Contract award
Spennymoor 400kV
National Grid Electricity Transmission PLC
Key facts
| Buyer | National Grid Electricity Transmission PLC |
|---|---|
| Notice type | Contract award (UK6) |
| Value | Not stated |
| Deadline | Not stated |
| Clarification deadline | Not stated |
| Procedure | Competitive flexible procedure |
| Category | Not stated |
| Region | London |
| Contract period | 3 Dec 2026 to 27 Dec 2028 |
| Suitable for SMEs | Not stated |
| Legal regime | Procurement Act 2023 |
| Published | 20 Nov 2026 |
Description (as published)
Spennymoor 400kV substation is a mesh corner configuration consisting of two single switch mesh arrangements. It is comprised of four 400kV transmission lines (Stella West 1, Stella West 2, Norton 1 and Norton 2), three 400/132kV 240MVA SGTs (SGT1, SGT2, & SGT3). The 400/132kV substation is owned and operated by The Client and comprises of an air insulated open terminal substation complete with all associated infrastructure, protection, control, telecommunications, ancillary equipment.
The Client has planned to extend the Busbar on MC4 and installation of NGET owned customer generator bay at Spennymoor 400kV to make provision for the User to connect their equipment. This has also triggered the retrofitting of the existing Stella West 2 line breaker to move the PoC from feeder protection zone to mesh corner protection zone.
The Contractor, shall also be responsible for supply, installation, testing and commissioning works for the grouting works to enable the extension of the compound at Spennymoor 400kv substation and at the non-operations land where the customer bay will be constructed.
Who won
- Costain Limited (SME)
Awarded value: 拢16m 路 awarded 3 Nov 2026