Contract award
Refurbishment of NLB Oban Base Store Roof
Northern Lighthouse Board
Key facts
| Buyer | Northern Lighthouse Board |
|---|---|
| Notice type | Contract award (UK6) |
| Value | Not stated |
| Deadline | Not stated |
| Clarification deadline | Not stated |
| Procedure | Below threshold - unknown |
| Category | Not stated |
| Region | Scotland |
| Contract period | 10 Nov 2026 to 29 Jan 2027 |
| Suitable for SMEs | Not stated |
| Legal regime | Procurement Act 2023 |
| Published | 5 Nov 2026 |
Description (as published)
A key objective of the project is to remove the last remaining asbestos from our Oban Depot. It鈥檚 believed that there is asbestos under the parapet coping stones. These large coping stones have to be carefully lifted to remove the asbestos from the underside. A full asbestos demolition survey is to be carried out at project commencement to identify all asbestos containing materials. The stone copes will be reset in their previous locations.
The existing roofing screed is to be fully stripped. Any defects to the existing substrate shall be repaired as necessary. A new waterproof/ non-slip coating will be applied over the substrate.
A new handrail is to be fabricated and installed around the inside face of the parapet.
A new aluminium step structure is to be fabricated and installed to allow access from the external kitchen door down on to the roof space.
Who won
- Accted Ltd (SME)
Awarded value: 拢176k 路 awarded 4 Nov 2026
CPV codes
Source: Find a Tender. Contains public sector information licensed under the Open Government Licence v3.0. Licence: Open Government Licence v3.0. We do not alter the facts of the notice; always check the original before bidding.