Provision of new HV electricity supply connections to Alice Holt Research Station
Forestry Commission
Key facts
| Buyer | Forestry Commission |
|---|---|
| Notice type | Direct award (transparency notice) (UK5) |
| Value | Not stated |
| Deadline | Not stated |
| Clarification deadline | Not stated |
| Procedure | Direct award |
| Category | Not stated |
| Region | South West |
| Contract period | 26 Oct 2026 to 22 Oct 2027 |
| Suitable for SMEs | Not stated |
| Legal regime | Procurement Act 2023 |
| Published | 16 Oct 2026 |
Description (as published)
Installation of a connection to the host DNO's (Scottish and Southern Electricity) electricity distribution network, involving the supply and installation of 11kV cabling and a substation and LV cabling and service position works and non-contestable works.
Who won
Awarded value: £268k
CPV codes
Source: Find a Tender. Contains public sector information licensed under the Open Government Licence v3.0. Licence: Open Government Licence v3.0. We do not alter the facts of the notice; always check the original before bidding.