Early Contractor Involvement for the Design for the Replacement of Middle Blackdene Footbridge

Durham County Council

Deadline (your time) ·

Key facts

Key facts
BuyerDurham County Council
Notice typeContract award
Value£41k
Deadline16 Mar 2026, 12:00
Clarification deadlineNot stated
ProcedureCall-off from a framework agreement
CategoryWorks
RegionNorth East
Contract period6 Jul 2026 to 4 Dec 2026
Suitable for SMEsNo
Legal regimeNot stated
Published21 Aug 2026

Description (as published)

Durham County Council (DCC) require a contractor to prepare and under-take a scheme to remove the existing sub-standard footbridge and install a replacement structure (comprising steel beams with FRP deck and parapets). The existing abutments are to be retained and modified/ repaired as required to accommodate the replacement deck. Further competition against Framework Agreement NEPO211 Civil Engineering & Infrastructure Works Framework - Lot 2.

Who won

Awarded value: £41k · awarded 27 May 2026

CPV codes

Source: Contracts Finder. Contains public sector information licensed under the Open Government Licence v3.0. Licence: Open Government Licence v3.0. We do not alter the facts of the notice; always check the original before bidding.